Nebius Signs as First Customer for VOLT's €7 Billion Rotterdam AI Gigafactory

The Amsterdam neocloud locks in a letter of intent for up to 200 MW and as many as 100,000 GPUs. VOLT still needs permits and financing before groundbreaking.

ROTTERDAM · Elena Vos, Business · Oct 13 2026

ROTTERDAM - Nebius Group has signed a letter of intent to become the first customer of VOLT’s planned AI gigafactory in the Port of Rotterdam, Dutch newspaper reporting via ANP confirmed Monday, giving the privately financed project the anchor tenant it needs before it can chase lenders for a €7 billion first phase.

According to De Telegraaf, Financieele Dagblad and TechTimes, the LOI covers long-term capacity for up to 200 megawatts and as many as 100,000 advanced AI chips. VOLT describes the first construction phase as two buildings of about 100 MW each. Roughly €2.5 billion would go to buildings and grid work and €4.5 billion to chips and compute kit, the company has said.

Nebius Group brand art from the company’s public assets. Image: Nebius

VOLT founder and chief executive Han de Groot told Dutch outlets that a project of this scale needs a named customer before investors and energy partners move. Construction is hoped for 2028 in some accounts, with first capacity often pegged to late 2029 or early 2030. Permits, financing and a binding lease are still outstanding. NL Times, citing FD, reported that Nebius can walk away if the project slips.

VOLT Rotterdam AI Gigafactory campus concept art. Image: VOLT

The campus sits on brownfield land at Maasvlakte / Europoort, where VOLT says an existing high-voltage connection can tap the 380-kilovolt transmission network rather than the congested local distribution queues around Amsterdam. Energy partner plans point to North Sea wind via Eneco, with other green contracts as backup. Full site ambition has been framed at up to 600 MW or 800 MW depending on the briefing, with six buildings in the larger design.

Europort industrial landscape at Maasvlakte, Rotterdam. Photo: Nitot / Wikimedia Commons

Screenshot: @dcdnews on X, Oct. 12, 2026

Nebius, traded on Nasdaq as NBIS, is headquartered in Amsterdam and already sells GPU cloud capacity under large Microsoft and Meta contracts. The Rotterdam LOI would be a first major Dutch compute footprint for a company that has been scaling elsewhere. VOLT also launched its Dutch AI Cloud from a NorthC facility in Amsterdam as a live, bookable sovereign GPU platform while the gigafactory remains on paper.

Wind turbines at Maasvlakte, the offshore-wind corridor VOLT cites for the campus. Photo: Wikimedia Commons / Panoramio

Wider view across Maasvlakte 2 toward the older port zone. Photo: Wikimedia Commons / Panoramio

Europe’s AI compute debate is the backdrop. The European Commission is running an InvestAI gigafactory tender, but the Netherlands declined that public path for this site. VOLT is pitching a fully private build. Nebius gives it a bankable name. Until permits close and a lease replaces the letter of intent, the €7 billion phase is still a financing story, not a construction one.